MODIFICATION
38 -- Lolo National Forest, Ninemile Ranger District, Stony Creek Culvert Replacement
- Notice Date
- 6/28/2010
- Notice Type
- Modification/Amendment
- NAICS
- 237310
— Highway, Street, and Bridge Construction
- Contracting Office
- Department of Agriculture, Forest Service, R-1 Western Montana Acquisition Zone (Lolo NF; Flathead NF; Bitterroot NF; Regional Office; Aerial Fire Depot), Building 24, Fort Missoula, Missoula, Montana, 59804
- ZIP Code
- 59804
- Solicitation Number
- AG-03R6-S-10-0048
- Archive Date
- 7/23/2010
- Point of Contact
- Lynette Band, Phone: 406-329-3856, Barbara E Venturini, Phone: 406-758-5318
- E-Mail Address
-
lband@fs.fed.us, bventurini@fs.fed.us
(lband@fs.fed.us, bventurini@fs.fed.us)
- Small Business Set-Aside
- HUBZone
- Description
- Western Montana Acquisition Zone anticipates awarding a fixed price construction contract for work involves removal of existing culvert and replacement with a 15’ span x 5’-8” rise structural plate arch culvert. Also includes placement of government furnished borrow excavation and riprap as well as contractor provided crushed aggregate and all required stream simulation work on the Ninemile Ranger District, Lolo National Forest, Missoula County, MT. All instream work performed under this contract can only be performed during the period of July 15th through September 1st. If work is started in 2010, the work must be completed by October 1, 2010; if work is to be performed in 2011 work shall be compelted by Octorber 1, 2011. Estimated price range is $ 25,000 to $ 100,000.) The solicitation will be available on approximately May 24, 2010, and can be downloaded from this site at that time.
- Web Link
-
FBO.gov Permalink
(https://www.fbo.gov/spg/USDA/FS/03R6/AG-03R6-S-10-0048/listing.html)
- Record
- SN02189731-W 20100630/100628234737-0820d388b1512638336ccbb94d36c77d (fbodaily.com)
- Source
-
FedBizOpps Link to This Notice
(may not be valid after Archive Date)