Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
FBO DAILY ISSUE OF APRIL 02, 2010 FBO #3051
AWARD

Z -- RECOVERY--Z--PROJECT NUMBER 2840, Center Hill Lake, TN Replacement of Control Cables at the Center Hill Power Plant, Project of the Nashville District U.S. Army Corps of Engineers.

Notice Date
3/31/2010
 
Notice Type
Award Notice
 
NAICS
237130 — Power and Communication Line and Related Structures Construction
 
Contracting Office
USACE District, Nashville, P.O. Box 1070, 801 Broad Street, Nashville, TN 37202-1070
 
ZIP Code
37202-1070
 
Solicitation Number
W912P510R0008
 
Response Due
3/15/2010
 
Archive Date
5/14/2010
 
Point of Contact
Isaac J. Taylor, 615-736-5679
 
E-Mail Address
USACE District, Nashville
(isaac.j.taylor@usace.army.mil)
 
Small Business Set-Aside
N/A
 
Award Number
W912P5-10-C-0006
 
Award Date
3/31/2010
 
Awardee
T.E.M. GROUP, INC. (848825766)<br> 3730 HIKES AVE<br> LOUISVILLE, KY 40218-2518
 
Award Amount
$3,292,525.00
 
Line Number
0001
 
Description
This contract action was accomplished using other than competitive procedures because a statute exists that expressly authorizes or requires that the acquisition be made from a specific source or through another agency (FAR 6.302-5); specifically, Sole source awards under the 8(a) Program. Per FAR 6.302-5 a J&A is not required for this award. 8(a) Direct Award-Project consists of furnishing all labor, equipment, materials, hardware, and miscellaneous items necessary to install temporary control cables for one generator, completely replace existing control and low voltage power cables, switchyard portion of control cable conduits, cable trays and sealing of seepage cracks that run through the Spread Room, Control cable tunnel and Power cable tunnel at Center Hill Power Plant. The Contractor shall verify that all new temporary and permanent cables to be installed be, as a minimum, technically and operationally compatible with the cables for which they are replacing, utilizing current state-of-art manufacturing standards, and in compliance with the most current national, state, and local standards or codes. The work covered by this section of the specifications includes, but is not limited to the following items: a. Furnish and install temporary control cables for the complete operation of one hydroelectric generator in such a way that generator availability is maximized during the balance of the project. Temporary cables shall be of the same size and insulation resistance as those originally installed. The cables shall be suitable for the environment they will be located in and will meet or exceed all NFPA 70: NEC 2008 requirements or other applicable standards and/or codes. Cables furnished and installed shall be new. b. Completely remove, furnish new and install all control and low voltage power cables that go through the Power Cable tunnel from origination point to termination point for the complete operation of the main hydroelectric generators. Replace, as needed, other control cables from origination point to termination point. The cables shall be replaced with the same size, length and insulation resistance as originally installed. The cables shall be suitable for the environment they will be located in and will meet or exceed all NFPA 70 requirements. The voltage of the cables varies and includes but is not limited to 125 VDC, 120 VAC, 220 VAC and 480 VAC. It is anticipated that cable insulation contains asbestos. c. Remove, furnish new and install all existing control cable conduits that originate in the cable tunnel to their termination points at the equipment they service in the switchyard for the complete operation of the main hydroelectric generators. The conduits shall be of rigid metal and galvanized to resist corrosion and of the same size as the conduit they are replacing. All conduit shall have fittings designed to cross expansion joints. All connection joints will be sealed to prevent the entrance of water. All bends and connections will be done in a professional manner by personnel experienced in working with conduit and will comply with existing NEMA standards and NFPA 70: NEC 2008 or other applicable standards and/or codes. Conduits furnished and installed shall be new. d. Remove, furnish new and install all cable trays located in the Spread room, Control cable tunnel and Power cable tunnel for the complete operation of the main hydroelectric generators. Cable trays contain asbestos and should not be sawed or broken). Cable trays should be replaced with new cable trays sufficient to sustain the load of the designated wiring. The new cable trays should be of the perforated or ladder design and have a finish that is designed for the environment they are located in. Cable trays shall meet or exceed NFPA 70: NEC 2008 or other applicable standards and/or codes. e. Seal seepage cracks in the concrete cable tunnels. Hydrophobic polyurethane grout shall be used. Crack sealing shall be performed after demolition of existing generator leads and prior to installation of new cable trays and generator leads.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA62/W912P510R0008/listing.html)
 
Record
SN02108121-W 20100402/100331235246-37db2bb490e2e41e7d30c08c71599da1 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.