FBO DAILY ISSUE OF MARCH 28, 2010 FBO #3046
AWARD

Y -- RECOVERY--Y--PROJECT NUMBER 137738, Peoria Riverfront Development, Illinois (Ecosystem Restoration) Upper Mid-sized Island Critical Restoration Project, Stage II, Illinois Waterway, River Miles 165.5 166.0, Tazewell County, Illinois

Notice Date
3/26/2010
 
Notice Type
Award Notice
 
NAICS
237990 — Other Heavy and Civil Engineering Construction
 
Contracting Office
USACE District, Rock Island, P.O. Box 2004, Clock Tower Building, Attn: CEMVR-CT, Rock Island, IL 61204-2004
 
ZIP Code
61204-2004
 
Solicitation Number
W912EK-10-R-0029
 
Response Due
3/11/2010
 
Archive Date
5/14/2010
 
Point of Contact
Brunson Grothus, (309)794-5241
 
E-Mail Address
USACE District, Rock Island
(brunson.e.grothus@usace.army.mil)
 
Small Business Set-Aside
N/A
 
Award Number
W912EK-10-C-0069
 
Award Date
3/25/2010
 
Awardee
MIDWEST FOUNDATION CORPORATION (050936475)<br> 22260 ILLINOIS RTE 9<br> TREMONT, IL 61568-1207
 
Award Amount
$3,815,600.00
 
Line Number
BASE BID & OPTIONS A, C, D, & F
 
Description
Contract Award Amount equals $2,350,000.00 Recovery Funds, and $1,465,600.00 Non-Recovery Funds. Solicitation W912EK-10-R-0029 has been awarded under contract W912EK-10-C-0069. Channels and backwaters areas of the Illinois River will be dredged using a high solids mechanical dredging methodology to varying depths. The dredged material will be placed inside of three rows of existing geotextile containers to construct an island. An additional row of geotextile containers will be placed on top of the existing geotextile containers and will be filled with dredged material using a high solids mechanical dredging methodology. Riprap will be placed to construct two rock closure structures and seventeen jetties adjacent to the island. During excavation, the contractor should expect to encounter debris such as trees, stumps, snags, metallic scrap, boat parts, tires, rope, cable, and other items that are commonly found in backwater areas of the Illinois River. The Contractor will separate and remove debris from the work site. Access from the navigation channel may be available by a previously dredged channel; however, the Contractor shall verify access requirements. All movement of floating plants may be restricted by shallow water. Peoria Riverfront Development, Illinois (Ecosystem Restoration) Upper Mid-sized Island Critical Restoration Project, Stage II, Illinois Waterway, River Miles 165.5 166.0, Tazewell County, Illinois.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA25/W912EK-10-R-0029/listing.html)
 
Record
SN02104590-W 20100328/100326235703-354797d15cf1abf68dc611bcf8a3b7e0 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.