FBO DAILY ISSUE OF OCTOBER 04, 2009 FBO #2871
AWARD

67 -- RECOVERY--67--Recovery - camera inspection of the relief wells, base contract.Recovery - Option 1 - camera inspectionRecovery - Option 2 - camera inspectionRecovery - Option 3 - camera inspection

Notice Date
10/2/2009
 
Notice Type
Award Notice
 
NAICS
541990 — All Other Professional, Scientific, and Technical Services
 
Contracting Office
US Army Corps of Engineer - Omaha District, 1616 Capital Ave, Omaha, NE 68102-4901
 
ZIP Code
68102-4901
 
Solicitation Number
W9128F09R0101
 
Response Due
9/14/2009
 
Archive Date
11/13/2009
 
Point of Contact
Kim M. Koenig, 701-654-7411
 
E-Mail Address
US Army Corps of Engineer - Omaha District
(kim.m.koenig@usace.army.mil)
 
Small Business Set-Aside
N/A
 
Award Number
W9128F-09-M-T043
 
Award Date
9/28/2009
 
Awardee
Atlas Inspection Technologies Inc.<BR>Eric Sullivan<BR>500 Elliott Ave W Ste A<BR>Seattle, WA 98119-4358
 
Award Amount
77,810.00
 
Line Number
0001
 
Description
1. GENERAL This scope of work (SOW) is for camera inspection services at Garrison Dam, North Dakota. Work generally consists of utilizing a remote operated camera to visually inspect 5 vertical relief wells within the powerhouse and several hundred feet of lateral drain pipes throughout the downstream embankment area, and producing a formal report to documents the condition of these features. Deliverables from this work will include DVD(s) of the inspection footage and a report that summarizes the procedures and findings of all inspections and includes individual inspection logs that summarizes the condition each pipe segment and documents the location of any significant observation. Detailed work requirements and the general execution of this SOW are provided below. All work shall be conducted in accordance with current professional standards, Corps of Engineers policies, regulations, and procedures, and the attached standard operating procedure (SOP). The Contractor is responsible for supplying all equipment, supplies, materials and personnel necessary for the completion of this work. 2.PERIOD OF PERFORMANCE AND BASELINE SCHEDULE The period of performance for the SOW shall be 6 calendar months from the date of Notice to Proceed (NTP). Upon receipt of NTP, the Contractor shall submit a draft baseline schedule for completion of the tasks in this SOW for approval to meet the milestones as indicated below. The baseline schedule shall be based on calendar days and shall include milestones for completion of each task provided herein.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA45/W9128F09R0101/listing.html)
 
Record
SN01979413-W 20091004/091002235714-176f58986a22d1c79425bb35e34b82dc (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.