AWARD
Y -- RECOVERY--Y--EMBANKMENT STABILIZATION AND SLIDE REPAIRS AT JOE POOL DAM, TEXAS.
- Notice Date
- 9/30/2009
- Notice Type
- Award Notice
- NAICS
- 237990
— Other Heavy and Civil Engineering Construction
- Contracting Office
- US Army Engineer District, Fort Worth, PO Box 17300/819 Taylor Street, Fort Worth, TX 76102-0300
- ZIP Code
- 76102-0300
- Solicitation Number
- W9126G09R0184
- Archive Date
- 12/9/2009
- Point of Contact
- DeYon Alexander Francis, 817/ 886-1046
- E-Mail Address
-
US Army Engineer District, Fort Worth
(deyon.a.francis@usace.army.mil)
- Small Business Set-Aside
- N/A
- Award Number
- W9126G-09-C-0082
- Award Date
- 9/30/2009
- Awardee
- SMR CONSTRUCTION, INC.<BR>801 K AVE, SUITE 11<BR>PLANO, TX 75074-1307
- Award Amount
- 2,000,103.00
- Line Number
- CLINS 7001 THROUGH 7008
- Description
- This contract action was accomplished using other than competitive procedures because a statute exists that expressly authorizes or requires that the acquisition be made from a specific source or through another agency (FAR 6.302-5); specifically, Sole source awards under the 8(a) Program. Per FAR 6.302-5 a J&A is not required for this award. This is a special notice to inform the public of the use of the Recovery Act funds. RECOVERY: THIS NOTICE IS PROVIDED FOR INFORMATIONAL PURPOSES ONLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO 8(a) CONTRACTOR SMR CONSTRUCTION, INC. The Contract Specialist for this action is Allen R. Bassett at 817-886-1051; or by e-mail at Allen.R.Bassett@usace.army.mil This contract action was accomplished using Other Than Full and Open Competition under the authority of FAR 6.302-5(b)(4), Sole source awards under the 8(a) Program15 U.S.C. 637 and the Partnership Agreement dated 1 February 2002 between the U.S. Small Business Administration (SBA) and the Department of Defense (DoD). The contractor shall provide all labor, supervision, tools, transportation, equipment, and materials necessary to repair upstream and downstream embankments at Joe Pool Dam. Work entails repair of eight slides along the downstream embankment of Joe Pool Dam via excavation and stockpiling of topsoil for reuse; excavate slide material, mix with lime, and replace the soil/lime mixture followed by compaction and seeding of disturbed areas. Removal and disposal of site concrete apron and guard posts at slide areas. Grading of benched shoreline areas to a uniform surface; apply geotextile filter fabric followed by application of bedding material; place riprap on repaired shoreline and tie in to exiting riprap.
- Web Link
-
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA63/W9126G09R0184/listing.html)
- Record
- SN01975515-W 20091002/091001000342-e159fa54f9374bcf5d1c5ef818eaefb5 (fbodaily.com)
- Source
-
FedBizOpps Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's FBO Daily Index Page |