C -- Design Services - Nevada Rail and Transportation

Notice Date
1/12/2004
 
Notice Type
Solicitation Notice
 
Contracting Office
Department of Energy, Bechtel SAIC Company, LLC (DOE Contractor), Yucca Mountain Project, 1180 Town Center Drive, Las Vegas, NV, 89114
 
ZIP Code
89114
 
Solicitation Number
PPD-SRA-0001
 
Response Due
1/26/2004
 
Archive Date
2/10/2004
 
Point of Contact
John Barr, Subcontract Specialist, Phone 702-821-7309, Fax 702-821-9002,
 
E-Mail Address
john_barr@ymp.gov
 
Description
PROJECT SPECIFIC PRE-QUALIFICATION Pre-qualification No. PPD-SRA-00001 Design Services - Nevada Rail and Transportation Yucca Mountain Project Due Date: January 26, 2004, 4:00p.m. PST INTRODUCTION: Bechtel SAIC Company, LLC (BSC) intends to issue a Request for Proposal (RFP) and to subsequently award a Design Services Subcontract for Nevada Rail and Transportation. It is BSC's intent to award a single subcontract for the services. However, BSC reserves the right to award multiple subcontracts if it is determined to be in the best interest of BSC, and the government, to cover the scope of services required. The RFP will be made available only to pre-qualified firms or teams. To potentially achieve pre-qualification and receive a RFP, respondents must submit: 1) a completed Federal Acquisition Regulation (FAR) Standard Form 254 (Architect-Engineer and Related Services Questionnaire) or equivalent, and 2) a completed FAR Standard Form 255 (Architect-Engineer and Related Services Questionnaire for Specific Project) or equivalent. Item 1) should be submitted for the lead firm (or for each lead firm if a joint venture) and for each consulting firm or independent associate on the team. Item 2) should be a single submittal on behalf of the entire team. Failure to complete a form may be reason for non-qualification of a team. SCOPE DEFINITION: As part of the Yucca Mountain Repository development efforts, the Department of Energy has announced the Caliente rail corridor as its preferred corridor in which to construct a rail line in Nevada, and Carlin as a secondary preference. If the Department adopts the mostly rail mode in Nevada, DOE will issue a Record of Decision selecting a rail corridor not sooner than 30 days after publication of the preference announcement in the Federal Register dated December 29, 2003. The primary Caliente Corridor originates at a junction with the Union Pacific mainline near Caliente, Nevada and extends 319 miles to the Yucca Mountain site (see Figure 1), located approximately 90 miles north of Las Vegas. The corridor is nominally 1/4 mile (400-meters) wide and consists of a "primary" corridor along with "secondary" options. After completing an Environmental Impact Statement (EIS), DOE will identify, in a Record of Decision (ROD), a single rail alignment within the corridor. Phases: Phase 1 - Conceptual Design (Approximately 12 months from a Notice To Proceed) Potential Options: Phase 2 (Potential Option) - Preliminary Engineering/Contract Documents (Approximately 24 months from end of Conceptual Design) Phase 3 (Potential Option) - Follow on Design Services (Approximately 40 months from start of design/build construction) Phase 1 - Subcontractor's Work Performance and Organization: The SUBCONTRACTOR shall perform at least 80% of the self-performed work (i.e. not third tier subcontracted work) at the SUBCONTRACTOR's offices in Las Vegas, Nevada The SUBCONTRACTOR shall provide office space, conference room space, furniture, equipment, and other facilities for the exclusive use of SUBCONTRACTOR's own project staff (including third tier subcontractor personnel) for the work scope herein defined and for the general use of the CONTRACTOR's Nevada Transportation project personnel. Such space shall ideally be situated within a 10 minute walking time of the existing BSC offices on Town Center Drive in Summerlin, Nevada, but in no event shall be more than 5 lineal miles from such location. The organization shall be lead by a permanent senior technical manager who shall be the principal point of contact between CONTRACTOR and SUBCONTRACTOR and shall be responsible for all aspects of the SUBCONTRACTOR's work. The senior technical manager shall coordinate, direct and manage all work performed by the SUBCONTRACTOR in CONTRACTOR's office in Las Vegas, at SUBCONTRACTOR's home office and third tier subcontract work wherever performed. It is anticipated that in the day-to-day conduct of the work, SUBCONTRACTOR's personnel will be interacting and communicating with counterparts, project engineers or managers within CONTRACTOR's staff. However, all work products and other technical deliverables shall be transmitted by SUBCONTRACTOR's senior technical manager to the CONTRACTOR's Nevada Transportation Project Manager. In addition, all technical correspondence concerning the conduct and execution of the work shall be between the SUBCONTRACTOR's senior technical manager and the CONTRACTOR's Nevada Transportation Project Manager and technical direction to the SUBCONTRACTOR will be provided only by the CONTRACTOR's Nevada Transportation Project Manager in writing. Phase 1 - Conceptual Design Tasks: 1.1 Requirements Review/Amendment 1.2 Design Criteria Review/Amendment 1.3 Photgrammetry and Aerial Mapping Review 1.4 Geotechnical Analysis Review 1.5 Hydrologic Analysis Review 1.6 Route Optimization Integration and Alignment Definition 1.7 Route Sections and Structures Design 1.8 Ballast and Trackwork Design 1.9 Track Schematic and UPRR Connection 1.10 Facilities Design (Control, Fueling, Sanding, Maintenance, Intermodal ) 1.11 Systems (Grade Crossings, Signaling, Communications, Asset Protection, Maintenance Equipment) 1.12 Permitting Requirements 1.13 EIS Interface Support 1.14 Construction Planning Support 1.15 Operations and Maintenance Planning Support 1.16 Technical Data Base Development Support 1.17 Cost Estimating Support 1.18 System Description and Critical Decision Process Support 1.19 Quality Assurance Program 1.20 Safety and System Assurance 1.21 Phase 2 (Preliminary Engineering) Work Plan 1.22 Management and Integration Phase 1 - Work Products (Deliverables) - Conceptual Design Drawings - Route Segments - Alignment Development Report - Design Analysis Report - Sections and Structures - Design Analysis Report - Ballast and Trackwork - Design and Operational Analysis Report - Track Schematic - Design Analysis Report - Maintenance and Other Facilities - Design Analysis Report - Railroad Systems - Permitting Requirements Analysis Report - Construction Implementation Planning Report - Operations and Maintenance Planning Report - Conceptual Design Phase - Quantities and Unit Cost Report - Conceptual System Description - Quality Assurance Program Plan - Quality Assurance Guidelines - Phase 2 (Preliminary Engineering) Work Plan Figure 1 Caliente Rail Corridor - Nevada This figure can be located in the full solicitation found at http://www.bscupdate.com/supplier_subcontractor/prequal.html LOCATION: The work will largely be performed in SUBCONTRACTOR's Summerlin, Nevada project office. PERIOD OF PERFORMANCE: The estimated RFP issuance date is February 2004. The anticipated date for award of the Subcontract is mid-April, 2004 with a Notice to Proceed provided at that time. See Scope Definition for project phase durations. SUBCONTRACT TYPE: It is anticipated that a cost plus fixed fee subcontract type will be used with an annual work plan authorization. The Order of Magnitude for Phase 1 of this work is estimated at $2.5 million for FY 2004. CONFLICT OF INTEREST: The questions shown in Table 1 must be responded to as part of the pre-qualification submittal. The questionnaire must be signed by the same individual signing the SF 254/255 Forms. PRE-QUALIFICATION PROCESS: To qualify to receive an RFP, the respondent must provide a positive response to the questions contained in Table 1. If the respondent answers any question negatively but attaches factual and verifiable information that respondent believes demonstrates avoidance of a conflict of interest or potential conflict of interest, BSC will evaluate such attached information, may verify same and will determine for itself whether a conflict of interest or potential conflict of interest exists or may exist. A panel of technical and procurement specialists within BSC will evaluate the completed Standard Forms 254 / 255, submitted by all respondents. The panel's judgement will be based solely on the completeness, relevance, quality and applicability of the data submitted by the respondents. EXCLUDED PARTIES LISTING SYSTEM: Confirm that your company is not listed on the U.S. Government's List of Parties Excluded from Federal Procurement and Non-Procurement Programs. Confirm that you are not aware of any current action by the Government, which would preclude your company for participating in this project. RESPONSE SUBMITTAL: Four (4) hard copies of the respondent's submittals, and one submission via e-mail, are required no later than 4:00pm (PST) on Monday, January 26, 2004. Include the name, title, address, telephone number, facsimile telephone number, and E-mail address of the responsible person to whom future communications should be addressed regarding the RFP. Address pre-qualifying documentation and all questions concerning this prequalification process to: Bechtel SAIC Company 1180 Town Center Drive Las Vegas, Nevada 89144 Attention : John Barr Pre-qualification No: PPD-SRA-00001 E-mail: john_barr@ymp.gov Fax: 702-821-9002 TABLE 1 CONFLICT OF INTEREST QUESTIONNAIRE 1) Will the respondent, during the potential term of the SUBCONTRACT, be under contract with or enter into a contract with, any other entity, public or private, directly involved with the Yucca Mountain Project in Nevada? __ Yes __ No If this question is answered by marking the "yes" box, then a full disclosure and discussion must be provided to allow BSC to evaluate the conflict of interest potential. 2) Will the respondent be under contract with, or enter into a contract with, the U.S. Department of Energy or U.S. Department of Energy's contractor or subcontractor at any tier, for any work directly involved with the performance of environmental analysis and the Environmental Impact Statement for the identification and selection of a specific rail alignment in Nevada? __ Yes __ No If this question is answered by marking the "yes" box, then a full disclosure and discussion must be provided to allow BSC to evaluate the conflict of interest potential. 3) Will the respondent be under contract with, or enter into a contract with, any railroad related facilities, systems or equipment Contractors or Suppliers under contract with the U.S. Department of Energy or U.S. Department of Energy's contractor or subcontractor at any tier, for any work item on the Nevada Transportation portion of the Yucca Mountain project, for which the respondent previously provided services as a part of the proposed Subcontract? __ Yes __ No If this question is answered by marking the "yes" box, then a full disclosure and discussion must be provided to allow BSC to evaluate the conflict of interest potential. The above is fact and intent: Company Name _______________________ Typed Name and Title _____________________ TABLE 2 AFFIRMATION _______________________________________________is not listed on the U.S. Government??s Lists of Parties Excluded from Federal Procurement and Non-Procurement Programs (Lists). (See U.S. Government website: http://epls.arnet.gov/) I am not aware of any current action by the government, which would preclude _______________________________________________from participating in this procurement. Company Name ______________________________ ____________________________________ Signature Typed Name and Title
 
Place of Performance
Address: Subcontractor's Summerlin, Nevada project office.
Country: USA
 
Record
SN00502136-W 20040114/040112211736 (fbodaily.com)
 
Source
FedBizOpps.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.